Project Finance Redefined

Key Highlights:

1. Lenders must ensure:

  • Financial closure and declaration of original DCCO (Date of Commencement of Commercial Operations) before any disbursement;
  • Disbursement schedule to be aligned with the project’s stage of completion in the loan agreement;
  • Realistic post-DCCO repayment schedule reflecting initial cash flows of Project.

2. Minimum lender exposure:

  • At least 10% if total exposure is up to ₹1,500 crore;
  • 5% or ₹150 crore, whichever is higher, if total exposure exceeds ₹1,500 crore.

3. All mandatory approvals applicable till financial closure must be in place before financial closure.

4. Adequacy of land/right of way before first disbursement.

5. A Techno-Economic Viability (TEV) study is mandatory for any modification in the original DCCO when aggregate exposure exceeds ₹100 crore.

6. A loan account can remain ‘Standard’ if:

  • DCCO is deferred up to 3 years (infrastructure) or 2 years (non-infra);
  • Cost overrun is within 10% of the original project cost (excluding IDC) - along with other conditions ;
  • Project cost rises by 25% or more due to a change in scope and size (excluding cost overrun) - along with other conditions and allowed only once in lifetime of Project.

7. Additional provisioning of 0.375% per quarter of DCCO deferment must be made over and above standard provisioning norms for standard accounts that have availed DCCO deferment.

This framework provides unified structure for project loan evaluation, enhances risk management, and facilitates early resolution of stress, thereby reinforcing credit discipline in infrastructure and project financing. This framework also promotes greater transparency among all stakeholders.

What Is a Power Purchase Agreement? How PPAs Work Under Indian Electricity Regulation

The Electricity Act, 2003, Explained: Which Parts Govern How Your Business Buys Electricity

Open Access Electricity in India: A Buyer's Guide to Eligibility, Approvals and Charges

What Is a Captive Power Plant? Captive and Group Captive Power in India After the 2026 Rules

Renewable Energy Certificates, Carbon Credits and Green Attributes: What C&I Buyers in India Actually Get from Green Power

What Is a Virtual Power Plant? How Aggregated Clean Energy Works, and Where India Stands